This page and subpages capture planning for Release.Next. This is higher-level than specific tasks (linked below).
Open Questions
- Is this 1.3 or 2.0?
New Build Process
The goal of modularizing and mavenizing was to make things easier for developers and consumers, but while we are in a halfway state things are probably worse.
What needs to be done:
- finish the Clojure on maven ticket DONE
- Get Hudson/Maven build + deployment working for Clojure & Contrib
- test the new contrib build against all the new contribs
- roll out the welcome mat for other new contribs
- approved new names are here
- solicit and respond to community feedback
Follow Along in JIRA
- Open / All issues for Release.Next
- Approved Backlog issues are not currently slated for the next release. Please add comments and/or vote up issues important to you!
Labels: